Exploration Program Schedule:

  • – Road clearing crew has been mobilized to the site to begin ground preparation for RAB drill program.- Road crews will re-open the historical roads and access points up to boundary of sensitive caribou management boundaries before July 15, 2021, thereafter, the clearing crews will continue into caribou management areas.- Proposed drill sites are being marked.- Geotech drill crew will arrive on site on July 15, 2021 and RAB drilling will commence on July 16 – 17, 2021.- The proposed RAB drill program will take up to 18 days to complete, pending delays from fire-danger stop-work protocols.- The line brushing crew will arrive on site to start clearing lines for the IP survey July 8, 2021.- The line cutting work will take up to 31 days to complete. (More details on IP surveys to be provided in a future news release). See the full release here.